107 Keelung City Marine and Water Environmental Pollution Prevention Plan and Marine Environmental Education Promotion Plan
Absrtact |
Summary of results
Project Name: 107 Keelung City Marine and Water Environmental Pollution Prevention Plan and Marine Environmental Education Promotion Plan
Organizer: Fulian Engineering Consulting Co., Ltd.
Schedule for signing the contract: March 26, 2007 to December 15, 107
Execution of quantitative target statistical interval: March 26, 2007 to December 15, 107
Since the signing of the project, the progress of various water environment inspections, inspections, promotion and administrative coordination matters have been carried out in accordance with the provisions of the contract, and the final goal has been successfully achieved. The contents of the work and the progress of the excerpts are as follows.
I. Inspection and control of the management of the business and sampling operations
(1) Liaison business
1. There are a total of 77 listed companies in the jurisdiction. After deducting the waterworks, some new facilities have not been operated, and no sewage treatment facilities have been set up, at least one inspection has been completed, and the achievement rate is 100%.
2. Business routine testing items include: pH, water temperature, SS and COD.
3. The project has completed 140 inspections and inspections and 121 inspections, and achieved an annual target of 120, with an achievement rate of 117 and 100%.
(2) Construction site
1. This work is based on the construction site with the control number and the project of "construction site runoff wastewater pollution reduction plan".
2. Routine inspection projects at the construction site include: pH, water temperature and SS. Check the inspection to see if the function of the grit chamber is normal.
3. The project has completed 20 inspections and sampling operations, and achieved an annual target of 20, with a completion rate of 100%.
(3) Concealed pipe: Inspect the waste pipe of waste (sewage) water in the Dawulun Industrial Zone, complete 3 announcements and sealing operations, and achieve 3 annual targets with a completion rate of 100%.
(3) Concealed pipe: Inspect the waste pipe of waste (sewage) water in the Dawulun Industrial Zone, complete 3 announcements and sealing operations, and achieve 3 annual targets with a completion rate of 100%.
2. Management of water pollution prevention and control in industrial areas
(1) Dawulun Industrial Zone
1. The sewage plant discharge water is completed once a month for inspection and sampling, and the total execution is 12 times, including 6 night inspections; the annual target is completed 12 times, and the achievement rate is 100%.
2. The surface runoff is completed once a season, and the total number of samples is 4 times. The annual target is reached 4 times, and the achievement rate is 100%.
(II) Six industrial zones: The discharge water of the sewage plant will be completed and inspected once a quarter, and the total execution will be 4 times. The annual target will be reached 4 times, and the achievement rate will be 100%.
3. Inspection and control of community sewage and public sewerage systems and counseling operations
(1) Auditing operations
1. Inspected the number of community-managed communities in the jurisdiction (including 7 schools), after deducting the non-operational (such as the construction of Yuda Construction and Boyuan Construction) and taking over (such as Guoyang Dadi Community, etc.) At least one inspection was completed, and the achievement rate was 100%.
2. Community testing programs include: pH, water temperature, SS, BOD, COD and E-Coli.
3. The project has completed 52 inspection and verification operations, achieving 50 annual targets with a completion rate of 104%.
(2) Improvement of the function of the sewage sewer system and building sewage treatment equipment
The team checked the community that detected abnormal water quality in the sewage treatment facilities last year, and has assisted the six Fujinghua and Fangdi communities to complete the improvement, and meet the discharge water standards. The community has reached the contractual requirements, and the achievement rate is 100%.
(3) The community permit is not extended and will be counseled, consulted and assisted in obtaining the permit.
This year, the work team has coached 6 communities whose community permits have been overdue, completed 5 community license extensions and 1 community access to public sewers. The number of community targets that have reached the contractual requirements is 25%, and the achievement rate is 250%.
(4) Checking the operation of the public sewerage system
1. The public sewage sewer in the jurisdiction is one of the Peace Island Water Recycling Centers.
2. Test items include: pH, water temperature, SS, BOD, COD and E-Coli.
3. The public sewage sewers are sampled once every 2 months for a total of 6 times; the annual target is achieved 6 times, and the achievement rate is 100%.
(5) Handling the briefing session and the propaganda guide for the formalization contract of the community sewage treatment equipment and facilities; it has been held in the conference room on the 2nd floor of the 6th/29th Keelung Cultural Center, completing one of the contract requirements and sending Environmental protection carrying 200 cups, the achievement rate is 100%.
4. Filing, investigation and checking of pollution sources
(1) The satellite positioning has been completed in the escrow management business, and the pollution source and the river station (including the Beigang River) and the drainage position map have been drawn.
(2) The papers and electronic files are established in all the auditing records of the plan, and quality control is carried out.
V. Tianyi River Water Quality Testing
(1) Water quality testing is carried out for the upper reaches of the Tianyu River (Qianziqiao), the middle reaches (the first season is the BMW Bridge, the Xianglong Bridge from the second season) and the downstream (Jinji Bridge).
(2) The testing items include: water temperature, pH, DO, SS, BOD, COD, NH3¬-N, mercury, arsenic, chromium, cadmium, lead, zinc, nickel, copper, total nitrogen, total phosphorus and so on.
(3) Tianyu River completed one sampling per season, totaling 12 points; achieving an annual target of 12 points, achieving a rate of 100%.
6. Continue to promote the licensing system
(1) Notifying the operator to apply for regular reporting
1. Establish special lines and resident personnel to be responsible for accepting applications for water pollution prevention and control licenses of public institutions.
2. In order to effectively manage the license documents of the management business within the jurisdiction, the work team will report the extension list for the past three months in the monthly work monthly report, and notify the cause or community by phone to avoid the cause. The circumstances of being overdue.
(2) Handling the water pollution prevention and control regulations
In the conference room on the 2nd floor of the Cultural Center of Keelung City on 6/29 and 10/5, a statute briefing session was held for the community and business, and 2 sessions of the contract were completed, and the achievement rate was 100%.
(3) Providing a list of permit extensions and review of the ring technician
The work team provides a list of the list of license extensions and the list of license expiration dates that have not yet been applied for extension in the monthly monthly report, and notify the cause or community by telephone as soon as possible.
VII. Water pollution control fee management
The work team cooperated with the EPD to provide 106 suspected water pollution fee collection services for on-site inspections (12), and another one of the Suiji hospitals. A total of 13 on-site inspections were carried out, and the achievement rate was 130. %.
8. Maintaining stable operation of water quality and quantity automatic monitoring and video surveillance facilities
This work is carried out by the resident staff to check the system connection daily, and if there are abnormal obstacles, the obstacles are eliminated to ensure the stable operation of the system.
9. Water pollution control system database control
For the "Water Pollution Source Information System", "Marine Pollution Prevention and Control System", "Development of Dynamic Webpages for EPD Training Officers" and "Administrative Environmental Protection Department Control Number Unified Management System" is equivalent to completing the work within one month Carry out the construction and update of the system.
X. Evaluation of Wastewater Treatment Facilities
At 8/17, 24 and 9/20, six sewage treatment plants in the six industrial zones of Keelung City, the industrial bureau of the Ministry of Economic Affairs, Dawulun and Ruifang Industrial Zone Service Center sewage treatment plant, Fuji Weaving Co., Ltd.
Five companies, including Yongsheng Development Industrial Co., Ltd. and Peace Island Water Recycling Center, conducted evaluation of waste water treatment facilities.
XI. Water Environment Watch helps the patrol team to operate
(1) After integrating the opinions of the patrol teams this year, the patrol team tools were enriched in November.
(2) Establishing a dedicated line and stationed personnel to receive the notification and grievances of the patrol team, and assist in case handling and document management. 38 notifications have been completed as of 11/15; 35 annual targets have been achieved with a completion rate of 109%.
(3) When the second statute briefing session was held, the team consulted and coached the volunteers for the 30 patrol members participating in the activity. Among them, Dawulun captain Huang Zhengwei was willing to participate in the volunteer training course, so it was completed. Consultation and counseling work, follow-up if there is an environmental volunteer training course within the jurisdiction, will refer to its participation.
(4) The work team selects the warm patrol team with rich culture, landscape and human history, and assists in the production of the story of the two patrol teams. It has already used the kanban to provide warm teams in November.
(5) The working team continues to use the communication or telephone to contact and accompany the Xiding River Guard Team.
(6) Two patrol team education trainings have been handled in the 6/25 False Warm People Activity Center and the 10/26 False Acura District Office; and the patrol team environmental education facilities were completed in the second training session. Watching.
12. River surface cleaning (at least 20 metric tons)
This work team completed 10.79 metric tons of river surface waste disposal this year, with a completion rate of 53.9%.
XIII. Sudden pollution support and treatment in water environment
The team has reported on 6/28 the “Emergency Response Procedure for Dead Fish or Water Body Discoloration in Rivers” and assisted in the completion of the “Emergency Response Procedure for Dead Fish in Rivers in Keelung City” on 9/15.
XIV. Drinking water source
|
---|---|
Keyword |
Keelung City Marine and Water Environmental Pollution Prevention Plan and Marine Environmental Education Promotion Plan
|